Mumbai Roads Monitor

Ward T

ES zone
as of 30 Oct 2026, 09:03 am IST
Total road projects
72
Overdue
11
Awaiting closeout
1
Not Started
0
Active
5
On Hold
0
Completed
55
Disrupted km
5.9

Overdue projects

Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.

RoadContractorDays overdueExpected end
Trimurti narayan society RoadM/s Gawar Construction Ltd22222 Mar 2026
Panchsheel Nagar RoadM/s Gawar Construction Ltd2058 Apr 2026
off V.B.Phadake RoadM/s Gawar Construction Ltd18330 Apr 2026
Sant Dnyaneshar RoadM/s Gawar Construction Ltd1767 May 2026
BD Shinde MargM/s Gawar Construction Ltd16815 May 2026
Jay Bhavani RoadM/s Gawar Construction Ltd16815 May 2026
Nahurgaonthan Road (Internal) from Nahur Goan Gym to Mangal Archana BldgM/s Gawar Construction Ltd16617 May 2026
Off MMM Road and Goshala RoadM/s Gawar Construction Ltd16617 May 2026
Redwood Teakwood RoadM/s Gawar Construction Ltd15924 May 2026
Navghar Road (Side Strips)M/s Eagle Infra India Pvt Ltd15231 May 2026
Veer Savarkar RoadM/s Eagle Infra India Pvt Ltd15231 May 2026

Contractors in this ward

  1. M/s Gawar Construction Ltd
    Currently overdue
    19%
    Overdue
    9
  2. M/s Eagle Infra India Pvt Ltd
    Currently overdue
    11%
    Overdue
    2