Mumbai Roads Monitor

Ward S

ES zone
as of 30 Oct 2026, 09:03 am IST
Total road projects
41
Overdue
2
Awaiting closeout
0
Not Started
1
Active
16
On Hold
0
Completed
22
Disrupted km
6.5

Overdue projects

Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.

RoadContractorDays overdueExpected end
90 feet Road behind Fish Market and opposite fish Market, Shivram ParkM/s Gawar Construction Ltd15231 May 2026
Paanch Mandir RoadM/s Gawar Construction Ltd15231 May 2026

Contractors in this ward

  1. M/s Gawar Construction Ltd
    Currently overdue
    20%
    Overdue
    2
  2. M/s Eagle Infra India Pvt Ltd
    Currently overdue
    0%
    Overdue
    0