Mumbai Roads Monitor
Ward S
ES zoneas of 30 Oct 2026, 09:03 am IST
Total road projects
41
Overdue
2
Awaiting closeout
0
Not Started
1
Active
16
On Hold
0
Completed
22
Disrupted km
6.5
Overdue projects
Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.
| Road | Contractor | Days overdue | Expected end |
|---|---|---|---|
| 90 feet Road behind Fish Market and opposite fish Market, Shivram Park | M/s Gawar Construction Ltd | 152 | 31 May 2026 |
| Paanch Mandir Road | M/s Gawar Construction Ltd | 152 | 31 May 2026 |
Contractors in this ward
- M/s Gawar Construction LtdCurrently overdue20%Overdue2
- M/s Eagle Infra India Pvt LtdCurrently overdue0%Overdue0