Mumbai Roads Monitor
Ward M/W
ES zoneas of 30 Oct 2026, 09:03 am IST
Total road projects
107
Overdue
1
Awaiting closeout
1
Not Started
6
Active
18
On Hold
1
Completed
80
Disrupted km
6.7
Overdue projects
Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.
| Road | Contractor | Days overdue | Expected end |
|---|---|---|---|
| Marvali Village Road | M/s Gawar Construction Ltd | 166 | 17 May 2026 |
Contractors in this ward
- M/s Gawar Construction LtdCurrently overdue2%Overdue1
- M/s Eagle Infra India Pvt LtdCurrently overdue0%Overdue0