Mumbai Roads Monitor
Ward M/E
ES zoneas of 30 Oct 2026, 09:03 am IST
Total road projects
88
Overdue
3
Awaiting closeout
0
Not Started
9
Active
35
On Hold
4
Completed
37
Disrupted km
19.3
Overdue projects
Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.
| Road | Contractor | Days overdue | Expected end |
|---|---|---|---|
| Bajiprabhu Deshpande Marg to Ramdev Mourya Marg Road between plot no 46 & 44, Shivaji Nagar | M/s Gawar Construction Ltd | 173 | 10 May 2026 |
| Janata Nagar gully No 3 | M/s Gawar Construction Ltd | 152 | 31 May 2026 |
| Shivaji Nagar Road No. 15 | M/s Eagle Infra India Pvt Ltd | 152 | 31 May 2026 |
Contractors in this ward
- M/s Gawar Construction LtdCurrently overdue7%Overdue2
- M/s Eagle Infra India Pvt LtdCurrently overdue8%Overdue1