Mumbai Roads Monitor

Ward M/E

ES zone
as of 30 Oct 2026, 09:03 am IST
Total road projects
88
Overdue
3
Awaiting closeout
0
Not Started
9
Active
35
On Hold
4
Completed
37
Disrupted km
19.3

Overdue projects

Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.

RoadContractorDays overdueExpected end
Bajiprabhu Deshpande Marg to Ramdev Mourya Marg Road between plot no 46 & 44, Shivaji NagarM/s Gawar Construction Ltd17310 May 2026
Janata Nagar gully No 3M/s Gawar Construction Ltd15231 May 2026
Shivaji Nagar Road No. 15M/s Eagle Infra India Pvt Ltd15231 May 2026

Contractors in this ward

  1. M/s Gawar Construction Ltd
    Currently overdue
    7%
    Overdue
    2
  2. M/s Eagle Infra India Pvt Ltd
    Currently overdue
    8%
    Overdue
    1