Mumbai Roads Monitor

Ward K/W

WS zone
as of 30 Oct 2026, 09:03 am IST
Total road projects
150
Overdue
9
Awaiting closeout
3
Not Started
0
Active
1
On Hold
0
Completed
137
Disrupted km
8.1

Overdue projects

Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.

RoadContractorDays overdueExpected end
Road from masjid to god gift towerM/s RPS Infraprojects Pvt Ltd16320 May 2026
Tanaji Malusare RoadM/s RPS Infraprojects Pvt Ltd15429 May 2026
Ceaser Road Side StripM/s Megha Engineering and Infrastructures Ltd15231 May 2026
Gaodevi Road (Gillbirt Road)M/s RPS Infraprojects Pvt Ltd15231 May 2026
Jagganath Pedhe Marg ( Old Fisheries Road)M/s Megha Engineering and Infrastructures Ltd15231 May 2026
Masjid Yasin MargM/s RPS Infraprojects Pvt Ltd15231 May 2026
Oshiwara Garden RoadM/s RPS Infraprojects Pvt Ltd15231 May 2026
S.V.Road (Side Strip) from Oshiwara to J.P.RoadM/s Megha Engineering and Infrastructures Ltd15231 May 2026
Tata compound road-IM/s RPS Infraprojects Pvt Ltd15231 May 2026

Contractors in this ward

  1. M/s RPS Infraprojects Pvt Ltd
    Currently overdue
    6%
    Overdue
    6
  2. M/s Megha Engineering and Infrastructures Ltd
    Currently overdue
    7%
    Overdue
    3