Mumbai Roads Monitor
Ward G/N
City zoneas of 30 Oct 2026, 09:03 am IST
Total road projects
29
Overdue
3
Awaiting closeout
0
Not Started
6
Active
5
On Hold
1
Completed
14
Disrupted km
4.2
Overdue projects
Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.
| Road | Contractor | Days overdue | Expected end |
|---|---|---|---|
| Manmala Tank Road | M/s NCC Ltd | 213 | 31 Mar 2026 |
| Khed Gully | M/s NCC Ltd | 152 | 31 May 2026 |
| Ram Maruti Cross Road | M/s GHV (India) Pvt Ltd | 152 | 31 May 2026 |
Contractors in this ward
- M/s NCC LtdCurrently overdue17%Overdue2
- M/s GHV (India) Pvt LtdCurrently overdue20%Overdue1