Mumbai Roads Monitor
Ward F/S
City zoneas of 30 Oct 2026, 09:03 am IST
Total road projects
35
Overdue
6
Awaiting closeout
0
Not Started
1
Active
7
On Hold
2
Completed
19
Disrupted km
5.2
Overdue projects
Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.
| Road | Contractor | Days overdue | Expected end |
|---|---|---|---|
| Vitthal Chavan Road | M/s NCC Ltd | 517 | 31 May 2025 |
| Abhuday Nagar Road No.1 | M/s GHV (India) Pvt Ltd | 152 | 31 May 2026 |
| Kuber Gally | M/s GHV (India) Pvt Ltd | 152 | 31 May 2026 |
| Principal Vamanrao Mahadik Road | M/s NCC Ltd | 152 | 31 May 2026 |
| S.M.Jadhav Road (Road No.2) | M/s NCC Ltd | 152 | 31 May 2026 |
| T.J.Road | M/s NCC Ltd | 152 | 31 May 2026 |
Contractors in this ward
- M/s NCC LtdCurrently overdue44%Overdue4
- M/s GHV (India) Pvt LtdCurrently overdue13%Overdue2