Mumbai Roads Monitor

Ward F/N

City zone
as of 30 Oct 2026, 09:03 am IST
Total road projects
75
Overdue
3
Awaiting closeout
0
Not Started
17
Active
14
On Hold
4
Completed
37
Disrupted km
6.5

Overdue projects

Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.

RoadContractorDays overdueExpected end
H R Mahajani RoadM/s NCC Ltd15231 May 2026
Mahila Ashram road.M/s NCC Ltd15231 May 2026
Road no 24BM/s GHV (India) Pvt Ltd15231 May 2026

Contractors in this ward

  1. M/s NCC Ltd
    Currently overdue
    22%
    Overdue
    2
  2. M/s GHV (India) Pvt Ltd
    Currently overdue
    3%
    Overdue
    1