Mumbai Roads Monitor

Ward E

City zone
as of 30 Oct 2026, 09:03 am IST
Total road projects
48
Overdue
1
Awaiting closeout
0
Not Started
21
Active
9
On Hold
0
Completed
17
Disrupted km
3.6

Overdue projects

Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.

RoadContractorDays overdueExpected end
Meghraj Sethi Marg (Morland Road to B J Marg)M/s NCC Ltd15825 May 2026

Contractors in this ward

  1. M/s NCC Ltd
    Currently overdue
    8%
    Overdue
    1
  2. M/s GHV (India) Pvt Ltd
    Currently overdue
    0%
    Overdue
    0