Mumbai Roads Monitor

Ward D

City zone
as of 30 Oct 2026, 09:03 am IST
Total road projects
73
Overdue
16
Awaiting closeout
0
Not Started
22
Active
4
On Hold
1
Completed
30
Disrupted km
6.8

Overdue projects

Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.

RoadContractorDays overdueExpected end
S K Rathod MargM/s NCC Ltd25715 Feb 2026
Babulnath 1st x laneM/s NCC Ltd24428 Feb 2026
Sadashiv LaneM/s GHV (India) Pvt Ltd22915 Mar 2026
11 th Khetwadi LaneM/s NCC Ltd21331 Mar 2026
JSS RoadM/s GHV (India) Pvt Ltd15330 May 2026
Khetwadi 10th lane (Maulana Shaukat Ali Road to Khetwadi Main Road)M/s GHV (India) Pvt Ltd15330 May 2026
13 th Khetwadi LaneM/s NCC Ltd15231 May 2026
Babulnath 3rd x laneM/s NCC Ltd15231 May 2026
Borbhat LaneM/s NCC Ltd15231 May 2026
Darabsha LaneM/s GHV (India) Pvt Ltd15231 May 2026
K M Munshi MargM/s NCC Ltd15231 May 2026
Kashibai Navrange MargM/s NCC Ltd15231 May 2026
Motibai Path (near Amar Hotel)M/s GHV (India) Pvt Ltd15231 May 2026
Mugbhat LaneM/s NCC Ltd15231 May 2026
V P RoadM/s NCC Ltd15231 May 2026
Wadia PathM/s GHV (India) Pvt Ltd15231 May 2026

Contractors in this ward

  1. M/s NCC Ltd
    Currently overdue
    63%
    Overdue
    10
  2. M/s GHV (India) Pvt Ltd
    Currently overdue
    20%
    Overdue
    6