Mumbai Roads Monitor

Ward C

City zone
as of 30 Oct 2026, 09:03 am IST
Total road projects
38
Overdue
4
Awaiting closeout
0
Not Started
8
Active
5
On Hold
0
Completed
21
Disrupted km
3.3

Overdue projects

Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.

RoadContractorDays overdueExpected end
Bhandari StreetM/s GHV (India) Pvt Ltd20310 Apr 2026
Panjrapole 1st LaneM/s GHV (India) Pvt Ltd15726 May 2026
Dr. Veigas StreetM/s NCC Ltd15330 May 2026
Islampura RoadM/s NCC Ltd15330 May 2026

Contractors in this ward

  1. M/s NCC Ltd
    Currently overdue
    29%
    Overdue
    2
  2. M/s GHV (India) Pvt Ltd
    Currently overdue
    11%
    Overdue
    2