Mumbai Roads Monitor
Ward C
City zoneas of 30 Oct 2026, 09:03 am IST
Total road projects
38
Overdue
4
Awaiting closeout
0
Not Started
8
Active
5
On Hold
0
Completed
21
Disrupted km
3.3
Overdue projects
Overdue is measured against BMC's own end date for the road, which is often a shared programme deadline (e.g. the pre-monsoon target) rather than an individual contract date.
| Road | Contractor | Days overdue | Expected end |
|---|---|---|---|
| Bhandari Street | M/s GHV (India) Pvt Ltd | 203 | 10 Apr 2026 |
| Panjrapole 1st Lane | M/s GHV (India) Pvt Ltd | 157 | 26 May 2026 |
| Dr. Veigas Street | M/s NCC Ltd | 153 | 30 May 2026 |
| Islampura Road | M/s NCC Ltd | 153 | 30 May 2026 |
Contractors in this ward
- M/s NCC LtdCurrently overdue29%Overdue2
- M/s GHV (India) Pvt LtdCurrently overdue11%Overdue2